GEA Liquid Processing is well-known for the supply of complete process
lines to the dairy industry. Over the years, GEA Liquid Processing has
also gained great insight and experience with the rebuilding and extension of
existing processing plants from a large number of successful rebuilding
projects.
Arla Foods Sweden was planning a radical structural change involving,
among other things, the transfer of production volume from a number of small
dairies to a few, big market milk dairies in Sweden, including Arla Foods’
dairy in Jönköping. As an experienced executer of rebuilding projects GEA
Liquid Processing was also asked to quote for the forthcoming rebuilding
of Jönköping Dairy.
Thorough Preparatory Work
From the start of the project
Arla Foods Sweden made the requirements to be met by the supplier absolutely
clear: Full functional and capacity responsibility, full responsibility for the
observance of the agreed time schedule, and a relatively long quotation phase
involving a considerable number of working meetings in which the project would
be successively adjusted up to the time of conclusion of the contract.
The conditions were difficult, but far from unknown to GEA Liquid Processing
who took up the challenge and established a homogeneous project group with a
100% dedicated project manager and responsible project engineers from Day 1 on
both the mechanical/process-technical side and on the electric/automation side.
Based on a feasibility study prepared by the client, GEA Liquid Processing
forwarded its first quotation to Arla Foods in October 2004. A considerable
number of clarification and coordination meetings were to be held before the
final concept was in place and Arla was ready to entrust GEA Liquid Processing
with the responsibility for the execution of the project in the early summer of
2005. However, the thorough preparatory work carried out in the initial phase
turned out to be returned tenfold later on, in the form of meticulous process-
and automation solutions – often with GEA Liquid Processing’ distinct
fingerprint –, detailed planning of all phases of the project and a clear
common understanding of the project’s goal.
Optimum Coordination
In order to ensure the required
criss-cross coordination – with the client, sub-suppliers and all other parties
involved at the dairy –intense meetings continued throughout the entire
project. In total 39 ordinary project meetings were held with the participation
of both the client and key-suppliers to the project – most of them in GEA
Liquid Processing’ project office with full office-, meeting-, and IT setup
established on the site in Jönköping.
Since the rebuilding project included many subphases, the project also
involved a large number of commissioning sessions – in total approx. 20
sessions which were all carried out successfully within the ordinary weekend
standstill period of max. 24 hours without any disturbing impact on the
operation of the dairy.
Full Flexibility
Full flexibility was one of the main
demands made on the rebuilt production plant, calling for not only an
extension, but also a drastic change of all parts of the production plant and
of its control system.
Today, each individual part in the rebuilt production plant can be
completely flexibly connected based on GEA’s unique valve concept, allowing for
optimum utilization of the equipment and quick shift from one product to
another.
However, flexibility was also key to the successful execution of the
project. In the course of the project period the main time schedule was adapted
26 times, and about 50 supplementary orders/project changes were discussed in
order to meet new requests from Arla Foods to match the given market situation.
In spite of the ongoing adjustments, a total overview and agreement on the
scope of the project was maintained throughout the entire project. Prior to the
start of the rebuilding work, all existing plant documentation available at
Arla Foods was imported into GEA Liquid Processing’ Bentley CAE system. Thanks
to the system, GEA Liquid Processing’ project group kept complete control of
all new components and all successively removed/relocated/replaced components.
To such an extent that Jönköping Dairy has subsequently purchased a Bentley CAE
system for its own future maintenance of the project documentation.
Sweden as Home Market
GEA Liquid Processing continually
executes projects in Sweden and is today as much at home in Sweden as in
Denmark. GEA Liquid Processing has established a close working relationship
with many Swedish sub-suppliers and has its own staff living in Sweden.
GEA Liquid Processing has used several Swedish sub-suppliers for the
rebuilding work at Jönköping Dairy, among them ÅF Benima who was entrusted with
the entire automation supply, and Systemsvets who carried out all installation
work. Commissioning was performed by both Swedish and Danish commissioning
engineers.
Customer and Partner
Rebuilding tasks are always a huge
challenge due to many unpredictable factors and the demand for the continued
operation of the production plant during the rebuilding period. A close and
trustful working relationship with the client is absolute vital for success. At
Arla Foods’ dairy in Jönköping this process proceeded optimally, and GEA Liquid
Processing’ project manager Michael Sørensen says with satisfaction: ”There was
this fundamental attitude from both the client’s and the supplier’s side that
we were to work together like a team and not work against each other – to
obtain a good result and to reach the goal on time”. And Arla Foods’ project
manager Ola Allvin adds: ”Rebuilding a dairy in operation is like carrying out
a heart operation on a running marathoner. It is only possible with a small,
compact team in which there is no doubt about who is doing what”.
“Rebuilding a dairy in operation is like carrying out a heart
operation on a running marathoner”
| Key Figures of the Project |
|
|
GEA Liquid Processing extension and rebuilding of Arla Foods’
dairy in Jönköping involved, among other things:
|
|
- Installation of over 1,100 new GEA product valves and instruments
- Removal of over 500 valves, instruments or agitators/pum¬ps with related
programs
- Rebuilding of existing product tanks
- Replacement of existing product tanks
- Connection and integration of 22 filling machines from various suppliers
- New raw milk silo tanks
- Extension of 2 CIP plants by bigger tanks and new CIP lines
|
- New milk and cream pasteurising lines
- Rebuilding and extension of existing product valve matrices
- Execution of 7,500 welds – all approved
- New production servers, complete with process reporting system
- New controllers, Satt Line Foocos
- Extension of Ethernet as well as 10 Profibus DP and 52 AS-i
control
network
- More than 200 control panels, operator stations, MCC panels and valve boxes
|
|
|
Most Important Sub-suppliers
|
|
|
Control System: Electric Hardware and Electric Installation:
Mechanical Installation: Tanks: |
ÅF Benima, Kalmar, Sweden KB EL-Teknik, Ry, Denmark Systemsvets,
Norrköping, Sweden Tankki OY, Ähtäri, Finland |
|